Guides · Timeline · All guides

Nine months, slab by slab

A G+1 home in Hyderabad takes 9–10 months from design sign-off to handover; a G+2 takes 11–13 months, and a G+3 roughly 13–16. Those numbers assume a clear plot, approvals moving on schedule, and a builder whose money is tied to milestones. Here is the week-by-week plan we build against, where the monsoon bites, and why a stage-verified payment schedule is the cheapest schedule insurance you can buy.

How long does each stage take on a G+1?

StageWhat happensTypical window
Design & approvalsFloor plans, structural drawings, TG-bPASS submission, agreement signedWeeks 1–6
Excavation & foundationDigging, footings, columns to plinth, plinth beamWeeks 7–12
Ground-floor structureColumns up, ground-floor roof slab cast and curedWeeks 13–18
First-floor structureColumns up, top slab cast and curedWeeks 19–24
Brickwork & plasteringWalls, lintels, internal and external plasterWeeks 23–30
Electrical & plumbingConduits, wiring, water lines, drainage, sump connectionsWeeks 27–33 (overlaps)
FinishingFlooring, doors and windows, painting, fittingsWeeks 32–40
HandoverSnag walk, joint inspection, warranty documents in handWeeks 41–42

Approval windows are indicative and depend on plot size and documentation — verify current processing norms on the official TG-bPASS portal. Stages overlap on purpose: wiring threads through the structure while plaster dries elsewhere.

One line in that table is non-negotiable: cast and cured. Every slab holds the schedule for its curing period, whoever is in a hurry. A builder who pours and moves on in three days is borrowing strength from your future walls — our guide on concrete curing explains why.

How much longer do G+2 and G+3 take?

Each extra floor adds one full slab cycle — about 5–7 weeks of structure — plus its share of brickwork, wiring and finishing. The totals compound like this:

BuildSlabsBuilt-up on 150 sq yd*Typical total
G+12≈2,300 sq ft9–10 months
G+23≈3,450 sq ft11–13 months
G+34≈4,600 sq ft13–16 months

*150 sq yd ≈ 1,350 sq ft of plot × ~85% ground coverage per floor. At Hyderabad's 2026 market range of ₹1,700–₹3,800 per sq ft, that G+1 lands at roughly ₹45–61 lakh — the full working is in our 2026 cost guide.

Time is also money at the rate card level: our packages run from ₹1,950 per sq ft (Standard) to ₹2,650 (Signature), with grey structure at ₹1,000–1,100 — see what each package includes. A longer build doesn't change the rate, but it changes how long your money is committed, which is why the duration table belongs next to the price table.

How does the monsoon change the schedule?

Hyderabad's monsoon runs roughly June to September, and it is selective about what it stops. Excavation in saturated soil is slow and unsafe. Slab casting pauses on heavy-rain days. External plastering and painting wait for dry walls. Internal work — wiring, plumbing, tiling — carries on. And curing concrete actually likes the wet.

The sequencing rule that follows: start excavation between November and February. Dry soil, fast foundations, and your structure tops out before the first June downpour. If your slab work must span July–September, plan a 2–4 week buffer instead of pretending the rain won't come. The rule holds across the city, whether your plot is in Kompally or Neredmet.

What does a delay actually cost you?

Delay is the biggest hidden cost in construction precisely because no one itemises it — the ones that do get itemised are in our hidden costs guide.

How do stage-verified payments keep the schedule honest?

Simple mechanics: when payment is released only after you verify a completed stage, the builder funds progress to unlock the next instalment. Speed becomes the builder's incentive, not just your hope. A calendar-based payment plan does the opposite — the builder gets paid whether the slab exists or not.

On our projects the loop is closed by people, not promises: a dedicated site engineer on every build, dated photo updates in your project's WhatsApp group, and your own walk on the slab before money moves. And because the 10-year structural warranty sits in the agreement itself, there is no incentive for us to rush a cure to hit a date — we are standing behind that concrete for a decade, against an industry default of one year.

BEFORE YOU DIG

Know the cost before you commit the calendar

The 60-second estimator gives you the honest range for your plot size and package — so the money plan and the month plan start together.

Get my estimate

Frequently asked

How long does it take to build a G+1 house in Hyderabad?

A G+1 house in Hyderabad typically takes 9–10 months from design sign-off to handover — about 6 weeks of design and approvals, 18 weeks of structure, and 16–18 weeks of brickwork, MEP and finishing. Clean documentation and a builder paid stage-by-stage keep it at the lower end.

Can I build a house in 6 months in Hyderabad?

A grey structure can be completed in roughly 5–6 months, but a fully finished G+1 in 6 months is not realistic without compressing concrete curing time — the one thing no honest engineer will cut. Treat a "finished in 6 months" promise on a full build with suspicion.

Which is the best month to start house construction in Hyderabad?

November to February is the best window to begin excavation in Hyderabad — the soil is dry and your foundation and early slabs finish well before the June monsoon. Starting in April–May pushes your most rain-sensitive work into the wettest months.

Does rain stop construction work in Hyderabad?

Heavy rain pauses excavation, slab casting and external plastering, but it does not stop everything — internal work continues, and ponded water actually helps concrete cure. If your structure work spans July–September, plan a 2–4 week buffer into the schedule.

How much delay is normal in house construction?

A slip of 2–4 weeks over a roughly 40-week build is normal — rain days, a late material delivery, a revised drawing. Drift measured in months is not; it usually signals a cash-flow problem, and a stage-verified payment schedule is your early-warning system because progress stalls before the next instalment falls due.

Estimate my cost See packages All guides